“A 2023 change in Maine law means that two of four Nexamp solar farm projects in Washington County will lose over half of their generating capacity when online.
Nexamp Communications Manager Keith Hevenor explained the company is continuing to work within the new framework and will try to modify those projects affected by the change in the net energy billing (NEB) law that now limits megawatt (MW) production for the farms in question to 1 MW or less.
Originally the projects in Lubec and Eastport were expected to produce 2.7 MW each, or enough power each to serve about 450-500 average single-family homes.”
Source: The Maine Monitor